British Steel was losing £700,000 a day last year when its Chinese owner announced plans to shut the steelworks at Scunthorpe. After Jingye rejected support to buy raw materials, the UK government stepped in with emergency legislation to take control of the plant.
But that was not the end of the crisis. The cost to the government of propping up British Steel is now more than £1.2m a day. Yet the £359m bill, the latest disclosed to parliament last month, may only be the start.
Nearly a year on, it remains unclear what will happen to the blast furnaces and rolling mills at the North Lincolnshire site, and the 4,000 workers who turn iron ore into the long steels required for buildings, bridges and railways. In the meantime, the government is covering more losses every day.
“In the short term, they are going to cost, so that £350m number is going to get bigger,” said Jon Carruthers-Green, a steel market analyst at MEPS International, a price forecaster. “If you want to keep blast furnaces, if you want to keep rail supply, then it’s going to come at a cost.”
The UK steel industry is in a rut. In 1970, the country produced 28m tonnes of steel. That fell to 4m tonnes in 2024, and to only 2.5m tonnes last year – the lowest output since the reign of Queen Victoria.
That fall was mostly caused by the temporary shutdown of Tata Steel’s Port Talbot steelworks as it switches from polluting blast furnaces to cleaner and more efficient electric arc furnaces (EAFs). The government’s official receiver is also in control of the arc furnaces at Speciality Steel UK (SSUK) in South Yorkshire after its collapse into administration last year, as well as trying to work out a path for British Steel.
“It’s a heck of a thing to take on – which they knew,” said one person close to the government. “There’s no easy answers here.”
Jingye barrier
The first obstacle is Jingye, which bought British Steel out of receivership in 2020. The Chinese company remains the legal owner, even if it does not have actual control.
Jingye is thought to have requested as much as £1bn in compensation in return for giving up ownership – a sum that most observers feel it is unlikely to receive for a loss-making plant.
Under Jingye’s ownership, British Steel has already had significant financial support from the government, including a previously unreported £120m grant in December 2022. Government documents said the award was “made in order to avoid a major economic shock to the Scunthorpe area, safeguarding jobs and securing a major investment for the UK”.
Jingye did not respond to a request for comment.
Yet officials are also wary of expropriating it. A government assessment last month of the British Steel takeover bill acknowledged that “a more interventionist approach by the government … could raise concerns among certain investors”. It added: “There is a possibility that foreign investors may be deterred, or that diplomatic criticism could arise if the intervention is perceived as market distortion.”
There was little sign of progress after Keir Starmer’s visit to Beijing last week. Even if Jingye can be bought off then there are still several stages that would be required for the government’s ultimate aim: to find another owner who will continue production at Scunthorpe.
The fate of SSUK, formerly part of Sanjeev Gupta’s troubled Liberty Steel empire, could be intertwined. It is understood that officials have expressed a preference for a single buyer for both British Steel and SSUK.
One attraction of that set-up would be that SSUK – potentially after investment in new casting equipment suitable for long products – could supply steel to the Scunthorpe rolling mills. Meanwhile the blast furnaces would be shut and EAFs built on the same site. Industry experts have said shifting to electric would help British Steel, because construction projects were increasingly looking for beams with lower associated carbon emissions.
Several hundred jobs would be retained in British Steel’s rolling mills during the transition, but unions are opposed to “fixing SSUK by doing in Scunthorpe”, in the words of one official. Job losses at Scunthorpe under a Labour government would be a damaging symbol in an area where Nigel Farage’s Reform last year won the Greater Lincolnshire mayoralty.
“It is essential that we maintain steelmaking in Scunthorpe,” said Alasdair McDiarmid, the assistant general secretary of Community, a steelworkers’ union. “Almost one year on, we need a resolution on the issue of ownership and clarity on the long-term future of the works. Our members on site have tolerated more than enough uncertainty, and want to see a cogent strategy in place for the business.”
In the longer term, the number of workers would inevitably fall. It could take years to build an electric arc furnace and connect it to the electricity grid, and arc furnaces do not require anywhere near as many workers, so unions would be pushing the government to invest in jobs in other parts of the business.
British Steel declined to comment.

No more ‘virgin’ steel
Several executives in the industry said the government may have to back down from one of its pledges when it took over Scunthorpe: retaining the capability to produce “virgin” steel from iron ore. Blast furnaces use coal to reduce iron ore to iron for steelmaking, but arc furnaces rely on scrap steel or ready-made iron (which would require extra billions of pounds to make in the UK).
The government still appears wedded to the idea that it must preserve iron-making ability. The impact assessment put it in stark terms: “In a time of trade wars or conflict, reliance on foreign (potentially adversarial) suppliers is a strategic liability.”
“If we’ve got to import everything we can be held to ransom,” said David Murray, a veteran metals executive. British Steel “does need to be protected and we need to accept the cost of that”, he said.
Cameron Pleydell-Pearce, a professor of materials science and engineering at Swansea University, said going for EAFs might make British production more resilient in some regards, because the UK has bountiful scrap metal.
However, “it’s not a clear yes or no position” on which technology would leave the UK in the strongest position, he said, arguing for a “more technology-agnostic look at the solutions” for Scunthorpe, including considering newer techniques for reducing iron ore.
A government spokesperson said: “This government is determined to support British steelmaking and our steel communities now and for generations to come, and last year we saved British Steel from collapse, protecting thousands of jobs.
“We are continuing discussions with Jingye to find a pragmatic, realistic solution for the long-term future of the site and will publish a steel strategy this year setting out how we can achieve a sustainable future for the sector.”

Whatever option is chosen, nobody involved expects a quick resolution to the Jingye problem – let alone a long-term owner. The interest declared by one possible buyer, the US-based retail investor Michael Flacks – who could reportedly combine Scunthorpe’s operations with another plant in Italy – took the government by surprise, given his lack of steel experience. Several industry sources said it was unclear what advantages a combination would offer.
However, officials insist privately that there is significant – albeit early – interest from others.
“A global steelmaker might [buy it], but they’d want to take on the finished article,” said Murray, with large government support in place. “They wouldn’t take it on as it is now.”
That means that the government may be in control of British Steel for some time yet. One person close to the situation said that it could take four or five years before it is back out of government hands.
Disclaimer : This story is auto aggregated by a computer programme and has not been created or edited by DOWNTHENEWS. Publisher: theguardian.com