Taxpayers were stung an extra $16.5 million for a Big Build level crossing removal project after former premier Jacinta Allan ordered builders to change their preferred approach and keep Frankston line express trains running ahead of the 2022 state election.
Planned track closures were instead pushed back to December that year – just days after voters went to the polls.
Documents obtained under freedom-of-information laws show that Allan, then the transport infrastructure minister, directed contractors on the Glen Huntly station level crossing removal project to rewrite their construction schedule to prevent express train cancellations from September to November 2022.
Those connected to the works said the move was taken by Allan because the Labor government feared a political backlash from bayside commuters at the November 2022 poll.
The decision saw builders delay work, run expensive night and weekend shifts, and pay out-of-hours penalty rates to catch up on time lost before the election, the FOI documents show.
It also meant more temporary resident relocations due to nighttime construction noise. The department initially estimated the move would cost between $22 million and $28 million but the eventual pricetag was $16.5 million.
“There are approximately 1600 residences within 100 metres of the rail corridor that may require relocation at various stages through the accelerated working period in 2023,” the advice to Allan said.
Under the original construction contracts for the Glen Huntly and Neerim Road level crossing removals, a dedicated express track on the Frankston line was scheduled to shut from July 2022 until the following June.
The closure was needed to allow massive piling rigs to drill 25-metre-deep foundations into the rail corridor safely without shutting the line entirely. It meant converting all Frankston services to stopping-all-stations for almost one year.
Passengers on city-bound Frankston-line trains spend up to 10 minutes longer on their journey if there are no express services. An express train from Frankston to the CBD will skip between 11 and 12 stops.
Briefing documents prepared for Allan in late June 2022 reveal she instructed the Level Crossing Removal Project (now known as the Victorian Infrastructure Delivery Authority, or VIDA) to find ways to reduce passenger disruptions.
Department officials presented Allan with several choices – explicitly noting that shutting express services would create a “significant disincentive” for commuters returning to the CBD post-pandemic.
Allan signed a brief authorising the spending in July 2022, which was 20 weeks before the November election.
Opposition MP James Newbury, who is likely to be attorney-general if the Coalition wins this Saturday’s state election, said Labor had “cynically cost taxpayers by delaying work in an effort to shore-up political favour in an election”.
“It’s obvious that the only reason for the delay was because of the election. And that political decision cost us all millions,” Newbury said.
A spokesman for Allan, the premier from 2023 to mid-2026, said the project was changed in 2022 following a recommendation by VIDA to minimise passenger disruption while keeping the overall project on course. Allan accepted this advice, he said.
To recoup the lost time, the government’s contractor, the Southern Program Alliance (consisting of Acciona, Metro Trains and Coleman Rail) accelerated construction after the vote, including intensive night shifts and extra weekend occupations of the railway line.
An independent estimator later reviewed the forecast costs, confirming that resequencing the piling rigs, paying overtime labour rates, rescheduling traffic management and organising residential relocations would cost millions more.
The $16.5 million in additional costs was added directly to the bill paid by the public for the project.
The extra spending on the Glen Huntly works came in the same month of 2022 that, according to claims aired in Victoria’s royal commission, Allan’s office was pushing contractors on another level crossing project to make peace with the CFMEU.
Witnesses last week told the royal commission into the Big Build that builder John Holland was warned it risked losing future state contracts unless it settled an industrial dispute that would add millions to the cost of the Sunbury Gap Road level crossing removal project – even as Allan’s department was preparing to spend millions to avoid disruption on the Frankston line.
Public Transport Users Association spokesman Daniel Bowen wrote on his blog in 2022 about rail shutdowns drying up in the lead-up to that year’s state election.
Interviewed on Tuesday about the 2022 Glen Huntly changes, Bowen said state governments had repeatedly avoided rail closures near elections since Labor lost in 2010.
The Frankston line was closed for rail maintenance on election day in 2010, when Labor lost five seats along the line – delivering victory to the Ted Baillieu-led opposition.
“We’ve certainly seen a pattern around the previous few elections where it appeared they were avoiding major works and rail line closures in the weeks heading up to the election,” Bowen said. “It hasn’t been the case this year, but certainly in previous election periods, there has been nearly zero rail line closures in the month heading up to the election day.”
A transport worker employed by one of the builders on the Glen Huntly project during its construction, speaking on the condition of anonymity, described the delay as a purely political intervention using public money.
“The real reason was: we don’t want to disrupt people’s journey in an election year. It was quite obvious that the decision was political,” the worker said.
Start the day with a summary of the day’s most important and interesting stories, analysis and insights. Sign up for our Morning Edition newsletter.
From our partners
Disclaimer : This story is auto aggregated by a computer programme and has not been created or edited by DOWNTHENEWS. Publisher: www.smh.com.au





